City of Arroyo Grande issued the following announcement on Feb. 10.

On December 14, 2021, the City Council approved a contract with Ferravanti Grading & Paving for the 2021 Street Repairs project. Ferravanti Grading & Paving will be performing street repairs on certain streets within the City, as listed below, during the months of February through May 2022. These improvements are part of a systematic program for maintaining, repairing and improving the streets within the City, and will consist of dig out patches to repair potholes and localized failures.

Street Segment

From

To

Corbett Canyon Road

State Route 227

City Limits (north of Gularte Road)

East Grand Avenue

Halcyon Road

El Camino Real

Fair Oaks Avenue

South Halcyon Road

Fred Grieb Bridge

South Elm Street

Ash Street

City Limits (south of Paul Place)

Valley Road

Sunrise Terrace

Los Berros Creek Bridge

Vernon Street

West Branch Street

End of Street (north of Larchmont Drive)

Wesley Street

West Branch Street

End of Street (north of Larchmont Drive)

North Halcyon Road

El Camino Real

East Grand Avenue

Rancho Parkway

West Branch Street

James Way

During construction there will be intermittent lane closures/shifting of traffic for safety purposes, but it is not anticipated that any roadway will be closed completely to vehicular traffic. Contractor will place informational barricades on the streets advising of specific dates and locations of parking restrictions. Please note that although the barricade may state certain hours, the actual construction work may occur at any time within that range. Normal work hours will be between 7:00 am and 5:00 pm, Monday through Friday, except for City holidays.

The street repairs may cause temporary inconvenience because of the nature of the work. The City appreciates your patience during this period and will attempt to minimize the inconvenience. Please contact the Public Works Department at (805) 473-5460 if you have special needs or concerns that should be taken into consideration during construction. If you have specific questions about the project, please contact Jill McPeek, Capital Improvement Project Manager at jmcpeek@arroyogrande.org or (805) 473-5444. The City will also have an inspector on site to address concerns you may have.